CHALLENGES
The 2500m2 wharf is a mix of hardwood timber, concrete and asphalt which required innovative demolition techniques.
The adjoining wharf was always to remain operational throughout the project, with both scheduled and unscheduled vessels berthing to offload containers 2-3 times per week. The stern of the vessels overhung the working area thereby requiring a collaborative approach to scheduling deconstruction works, minimising down-time as much as possible.
The quality of the wharf was severely undermined, limiting the weight allowed on deck.
Demolition of a wharf in an operational port facility presents environmental hazards that need to be carefully considered. The technique of demolition was aligned with the environmental considerations through lack of vibrations, total ban of chain sawing, minimal debris and minimal slurry output. Cutting off boats or barges was also prohibited.